Date |
Event |
Time |
 |
Dec 7 |
Door Knock |
8am-10am |
|
Dec 8 |
Move out House |
9am-4pm |
|
Dec 9 |
Demolish House |
1pm-4pm |
Dec 9 |
Remove concrete foundation |
3pm-6pm |
Dec 9 |
Build foundation pad |
6pm-9pm |
Dec 9 |
Dig footings |
8pm-10pm |
Dec 9 |
Form foundation |
9pm-11pm |
Dec 9 |
Under slab plumbing |
10pm-1am |
|
Dec 10 |
Under slab electrical |
12am-1am |
Dec 10 |
Plumbing Inspection |
12am-1am |
Dec 10 |
Stage pump truck |
1am-2am |
Dec 10 |
Pour/finish foundation |
2am-4am |
Dec 10 |
Seal and cure slab |
4am-5am |
Dec 10 |
Slab cure time |
4am-8am |
Dec 10 |
Set wall panels |
8am-2pm |
Dec 10 |
Set roof trusses/sheath roof |
2pm-10pm |
Dec 10 |
Window/door install |
6pm-9pm |
Dec 10 |
Rough plumbing |
8pm-3am |
Dec 10 |
Rough HVAC start |
8pm-3am |
Dec 10 |
Rough in electrical |
9pm-4am |
|
Dec 11 |
Rough electrical/HVAC/Electrical inspect. |
1am-2am |
Dec 11 |
Insulate walls and ceilings |
1am-6am |
Dec 11 |
Siding install |
6am-6pm |
Dec 11 |
Hang,tape, sand drywall |
7am-7pm |
Dec 11 |
Prime interior of house |
7pm-9pm |
Dec 11 |
Paint top coat |
8pm-12am |
Dec 11 |
Tile install |
10pm-6am |
Dec11 |
Install interior cabinets |
11pm-6am |
|
Dec 12 |
Begin interior millwork |
12am-7am |
Dec 12 |
Paint interior walls and trim |
6am-12pm |
Dec 12 |
Start landscaping |
8am-7am |
Dec 12 |
Install HVAC trim, final A/C install |
12pm-7pm |
Dec 12 |
Install plumbing fixtures, final |
12pm-7pm |
Dec 12 |
Install electrical fixtures, final |
12pm-7pm |
Dec 12 |
Install door hardware |
4pm-7pm |
Dec 12 |
Install appliances |
4pm-6pm |
Dec 12 |
Install wood floor |
10pm-6am |
|
Dec 13 |
Install shoe mould |
6am-9am |
Dec 13 |
Final clean/ clean windows |
8am-2pm |
Dec 13 |
Final Inspection |
10am-11am |
Dec 13 |
Keys given to Extreme Makeover |
2PM |
Dec 13 |
Furniture move in |
2pm-4pm |
Dec 13 |
Punch out and picture install |
7pm-12am |
Dec 13 |
Install mini blinds |
7pm-10pm |
 |
Dec 14 |
“Move That Bus!” |
2PM |
|
Dec 15 |
Clean up day |
All day |
|
Dec 16 |
Clean up day |
All day |